Olney Retail Park for Park lodge Construction
Groundworks package for 2 x warehouse units and offices off Stilebrook Road in Olney. There was a substantial difference in height of the neighbouring property making the use of PC Retaining wall units essential for this project.
Client
Park Lodge Construction
Project Type
Drainage
About The Project
Connection into FW and SW systems via 3m deep manholes, all signed off with local water authority and sewers for adoption standards, Internal FW system outfall into septic tank and external SW system into crate soakaways via oil bypass separator.