Morris Homes and Shelbourne Estates project along Houghton road A1123. The grounds are within a tree lined entrance access road and large spacious woodland area. Swales and ponds cut and graded finished within the grounds and landscaped.

Client

Morris Homes

Project Type

278 Works

About The Project

New access road into development rising main and connection into existing sewer in highways Works consisting of : Reduce level dig to formation and testing, New Rising main sewer at 4/5metres deep including air valve chamber and gravity fed pipework to connection into highways. SW Drainage installed into existing, Beany channels and kerbs with sump, All new kerb and edgings installed, stone , tarmac to finishes.