Olney Retail park for Lodge Park Construction

Groundworks package for 2 x warehouse units and offices off Stilebrook Road in Olney. There was a substantial difference in height of the neighbouring property making the use of PC Retaining wall units essential for this project.

Client

Lodge Park Construction

Project Type

Retaining Walls

About The Project

RC foundation along neighbouring land, Placement and installation of the pre cast concrete units by drilling and cemfixed in position with dowel bars Steps at varied intervals to follow existing neighbouring land, keeping line and level for quality checks.